Whole life carbon compliance no longer ends at design stage. Under BREEAM UK New Construction V7 and the GLA's London Plan guidance, a scheme has to show that the building as constructed performs as the design-stage assessment predicted, and that the assumptions made at planning have turned into measurable carbon outcomes. That is what an as-built whole life carbon (WLC) verification does. Below is what it involves and what the two regimes ask for.

The as-built model is the proof point

A design-stage WLC assessment rests on forecasts, provisional specifications and tender data. By completion, procurement decisions, value engineering and material substitutions have all changed the picture, and the as-built model is where their effect on embodied carbon is finally confirmed.

For BREEAM V7, an as-built WLC model is now the expected submission, and the Mat 01 credits that depend on post-construction verification cannot be secured without one. Three other parties increasingly expect it too:

  • GLA planning officers, through the Whole Life Carbon Reporting template
  • ESG investors, who want performance data they can verify
  • clients, who want evidence that the carbon reductions were achieved, not merely modelled

How we rebuild the model

We do not re-run the original design model with a few updated quantities. We rebuild it from the as-built record: verified quantities, procurement records and manufacturers' EPDs, so that the final carbon model describes the building that was actually constructed.

The process has four steps.

Step What we do
Data reconciliation Compare the assumptions made at design stage with the actual procurement data and construction records
Material verification Check each EPD and embodied carbon factor against certified datasets
Variant tracking Quantify the effect of substitutions, changes and value engineering decisions
Final reporting Issue an auditable WLC report suitable for the BREEAM Mat 01 submission and for GLA post-completion evidence

The result is a carbon figure rooted in verified data, which assessors, planners and investors can rely on because someone independent has checked it. It also tells the team what changed between design and construction and why, and that is the feedback that improves design and procurement decisions on the next project. The same model supports compliance with BREEAM V7, the GLA guidance and the Net Zero Carbon Building Standard.

What BREEAM V7 and the GLA require

Under BREEAM V7, a life cycle assessment is required at three stages: concept, technical design and as-built (BREEAM V7 launch documentation, July 2025). The GLA requires a post-construction assessment, typically three months after project completion and before handover (Section 3.14 of its guidance).

The GLA's WLC guidance also sets minimum evidence for the post-construction assessment:

  • site energy use records, including fuel
  • contractor confirmation of as-built material quantities and specifications
  • material delivery records, including transport details
  • waste transport records, including quantities and modes of transport

The post-construction assessment must update the figures submitted at planning (RIBA Stage 2/3), compare them with the original estimates and explain any variance (Section 3.16). The GLA's review then looks at completeness, technical robustness (its own word for it), the scale of the emission reductions achieved and the overall level of ambition (Section 3.18).

An as-built WLC model turns a projected target into a proven outcome, and that closes the gap between design intent and delivered performance. ADW Developments provides the independent verification that lets embodied carbon evidence stand up to technical and regulatory assessment.