The Construction and Demolition sector generates over one-third of all waste arisings in the UK and the wider world. Regulation of the sector through pre-demolition auditing and surveying can allow schemes to identify and quantify the types of material waste to be generated, and to further develop evidence-based strategies on how the material waste can be minimised.
What to expect from a pre-demolition audit
A pre-demolition audit quantifies the expected waste to be generated from the demolition. It then strategises how it can be best managed with the aim of encouraging circular economy options. It also identifies waste material that can be reused in the new construction or refurbishment, material that can be recycled to support a circular construction economy, and material that can be diverted from landfill into more productive uses. Furthermore, the audit supports a conventional Resource Management Plan (RMP) by adding evidence-based information about recycling and key demolition products which can be practically considered in the project plan.
ADW Developments expertise
ADW Developments has substantial expertise in conducting pre-demolition audits that support an efficient construction waste management strategy. This includes the following:
- Setting key targets for recycling and reuse
- Identifying and recommending local recyclers
- Determining landfill diversion for key materials
Lastly, a salient benefit of a pre-demolition audit is that the process identifies opportunities of material re-use. This allows the scheme to recoup a significant volume of valuable materials through reuse and recycling which would otherwise need to be purchased new, thus promoting passive cost-savings in the scheme overall.
When to commission it
At RIBA Stage 2 or early Stage 3. At that point a full, quantified audit still feeds the cost plan and the programme, and the reuse options it finds can still change structural or specification choices. At Stage 4 the design is fixed and the procurement decisions are made, so the same audit satisfies the planning requirement and changes nothing else.
The audit has to be finished before demolition contracts are let. Once a contractor is appointed and the method is fixed, targeted deconstruction is hard to deliver, and the saleable steel, timber, brick and curtain walling go out as mixed waste at landfill tax rates.
On referable London schemes the audit is also the evidence base for the Circular Economy Statement required under Policy SI 7. A statement cannot be written back from the design: it has to show the existing building was treated as a resource, and without an audit there is nothing to show.
What the report gives you
- A material inventory by element, with estimated volumes or weights
- The condition of each material and whether it suits direct reuse, secondary use or recycling
- Hazardous materials that need specialist handling, such as asbestos and lead paint
- Estimated disposal costs and recovery income by material
- Recommendations on deconstruction method and sequence
- Data in the form the Circular Economy Statement and the cost plan need it